Wind Turbine Construction Schedule
The St Croix Reformed Church will hold a brief GROUNDBREAKING CEREMONY for our 10 kw Wind Turbine this Sunday November 13th.
Preliminary Construction Schedule:
Nov 13th: Ground Breaking
Nov 14-24: Digging and pouring of the tower slab.
Late November: Digging and installation of electrical cables. Installation of electrical converters.
Mid December: Bolting of the tower to the slab. Assembly of the turbine to the tower.
“Turning it on” Party ….t.b.a.